Customer project – Steel Building Workshop, Shropshire.

Our client had recently moved from the south East to Shropshire and need a suitable workshop. To continue building his miniature steam engines.

What we provided

Steel Buildings provide the ground works, steel Workshop and installation of the workshop.

Steel Buildings provided an Insulated Composite Roof, with none insulated wall sheets. The client wanted to save money, by insulating the walls himself. While fitting out the internal of building.

Height to low eaves 2.5m
Overall outside of cladding Gable Width 8m
Overall outside of cladding Length 15m
Roof Pitch 12 degrees
Building Style Ridge
Number of Bays 4
Cladding type roof

Cladding Type Left Gable

Cladding Type Right Gable

Cladding Type Front Elevation

Cladding Type Rear Elevation

100mm Core Composite Panel – 135mm O/A
Non insulated Plastisol 0.5 without Anti Con
Non insulated Plastisol 0.5 without Anti Con
Non insulated Plastisol 0.5 without Anti Con
Non insulated Plastisol 0.5 without Anti Con
Rain water system Trimline – Juniper Green BS12B29

Main roller door of workshop

Colours Chosen

Flashings/Trim Juniper Green BS12B29
Roofing Cladding Juniper Green BS12B29
Wall Cladding Juniper Green BS12B29

Doors & Openings

Front elevation

  • 1no. Industrial Roller Door, manufactured from 0.7mm 75mm Galv laths.
  • Supplied with 100mm top Brushes and Bottom Seals as standard.
  • To suit an opening 3000mm wide x 2100mm high
  • Colour Coated – Juniper Green BS12B29
  • 1no. Single PA steel security door, powder coated.
  • Hinged on the right and opening outwards as you view the door from inside the building.
  • Structural Opening – 920mm wide x 2075mm high
  • Door Frame – 910mm wide x 2065mm high
  • Colour Coated – Juniper Green BS12B29